UNITS 7-10, MILTON PARK

Location: Units 7-10, Park Drive, Milton Park, Abingdon, Oxon OX14 4RR

Type of contract: JCT with CDP element

Overview:

We were required to undertake a major scheme to stabilise and repair all 4 units due to subsidence, cracking, water ingress and masonry failure. 

The internal refurbishment works were extensive and followed on from the major works package for this project which involved the complete underpinning of all 4 units. These works included the erection of a party wall between each unit; corrective works to the drainage system which had been installed by the original D&B contractor; a new VRF system was introduced to all 4 units including the construction of a piled plant deck between the units with the remaining services being reinstated to the units.  

Externally, the 4 units had their render removed in locations where the masonry had failed. We had to crack stitch the flank walls at multiple locations along the facades, the units were then rerendered and decorated. 

All of these works were part of the CDP element. 

This successful project allowed the landlord to move tenants back in and market the remaining units.